Progress
 
 
Project Details
DAR-2018-001185
CCP/Ngathal-Saikot/59
Impvt. of road from Ngathal to Saikot road
2016-11-17
PWD
Churachandpur
78.00
59
State Plan
Completed
2016-17
24.324595111225744,93.71119711784365
Progress Update : 2020-02-14
Completed
2016-17
soccpr1
24.324595111225744,93.71119711784365
24.3240358,93.7016728
0.96699732034671
Approved
2020-03-07 09:52:26
se1pwd
0
Road work

Progress Update : 2020-02-14
Completed
II
soccpr1
24.324595111225744,93.71119711784365
24.3168813,93.6453115
6.7305342093726
Approved
2021-12-23 07:04:23
se1pwd
59
Road work

Progress Update : 2018-09-26
Comleted
II
robert1
24.324595111225744,93.71119711784365
24.3236777,93.7019753
0.93989950883171
Approved
2021-12-23 07:07:52
se1pwd
59
Road work/GSB

Foundation & Inauguration
-
-
-

-
-
-