MSPDCL-TML-001
Supply, Installation and Commisioning for providing of Electric Power Connection at Security posts K-senam,Sehjang & Thingkhojang CRPF camp on NH-37
14/03/2016
POWER (MSPDCL)
Kangpokpi
144.52
131.90
DEPOSIT WORK
Completed
Phase 1
24.48248,93.55586
1.Construction of 11 KV line -20.0 km 2. Installation of Distribution Transformer -100 KVA -3 nos 3. Construction of LT-Line 1 Phase 2 wire 2.1 km 4. Construction of LT-Line 2 phase 3 wire 2.1 km 5. Construction of LT-Line 3 Phase 4 wire 2.1 km
Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.8053117,93.7349733
40.201411994889
0
K.Sinam CRPF post 86Bn 11 kv line.

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.7941333,93.6713417
36.565315558699
0
Sehjang CRPF post 86Bn 11kv line .

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.7942083,93.6709267
36.55985435371
0
Sehjang CRPF post 86Bn 11kv line .

Progress Update : 12/07/2017
Completed
Phase 1
TMLMA1
24.48248,93.55586
24.7946117,93.6727783
36.662261221068
0
Sehjang CRPF post 86Bn 11kv line .