Progress
 
 
Project Details
DAR-2018-000849
IED/culvert-Sambei/216
Constn. of 1.5m span RCC slab culvert at 9.80 Km (Near Sambei) on Imphal Saikul Road
2018-03-24
PWD
Imphal-East
20.00
10
State Plan
State work
2
24.90911511686125,93.98696840682373
Progress Update : 2020-03-02
State work
2
robin
24.90911511686125,93.98696840682373
24.9100201,93.9832188
0.39129253000153
Approved
2020-03-02 06:49:02
se1pwd
0
Completed

Progress Update : 2020-03-02
Completed
2
robin
24.90911511686125,93.98696840682373
24.9100201,93.9832188
0.39129253000153
Approved
2021-10-12 10:43:53
se1pwd
10
Culvert

Progress Update : 2018-03-28
On going
1
robin
24.90911511686125,93.98696840682373
24.90907094,93.9869755
0.0049627984609917
Approved
2018-03-28 06:02:54
ace3pwd
0
State work

Foundation & Inauguration
-
-
-

-
-
-