Progress
 
 
Project Details
DAR-2018-000772
MQCD/DARPAN/IIIT/TEMP/BH-3/33
Construction of Boys hostel, Girls hostel and classrooms at IIIT -Manipur (SH: Renovation of Existing Building for Boys Hostel No. 3)
2017-04-19
PWD
Imphal-East
285.40
91.2
State Plan
Ongoing
2nd
24.841537108013906,93.94266772270225
Earthwork in excavation, PCC work, full brickwork in foundation, half brickwork, doors and windows, flooring, false ceiling, plastering, wall tiles, painting, roofing, wood work in trusses etc
Progress Update : 2018-06-02
Ongoing
2nd
aemqcd1
24.841537108013906,93.94266772270225
24.8416785,93.9424608
0.026136138678788
Approved
2018-06-08 09:16:29
se2pwd
91.1966
Construction of line drain, rain water pipe, c.g.i sheet roofing, etc.

Progress Update : 2018-06-02
Ongoing
2nd
aemqcd1
24.841537108013906,93.94266772270225
24.8414338,93.9425912
0.013840366599386
Approved
2018-06-08 09:16:44
se2pwd
91.1966
Construction of line drain, rain water pipe, c.g.i sheet roofing, etc.

Progress Update : 2018-03-26
Ongoing
1
aemqcd1
24.841537108013906,93.94266772270225
24.8414981,93.9425433
0.013282502106061
Approved
2018-03-28 09:54:33
se2pwd
0
Boy's hostel toilet- Laying vitrified floor tiles, providing wooden doors, wash basin,etc.

Progress Update : 2018-03-26
Ongoing
1
aemqcd1
24.841537108013906,93.94266772270225
24.8414981,93.9425433
0.013282502106061
Approved
2018-03-28 09:56:26
se2pwd
0
plain AC sheet ceiling, painting, wooden doors etc.

Progress Update : 2018-03-26
Ongoing
1
aemqcd1
24.841537108013906,93.94266772270225
24.8414981,93.9425433
0.013282502106061
Approved
2018-03-28 09:58:14
se2pwd
0
Fixing collapsible sheet shutter, roofing with CGI sheet,contruction of plinth proctection line drain,etc.

Foundation & Inauguration
-
-
-

-
-
-