Progress
 
 
Project Details
DAR-2018-000486
IED/Retaining wall-Lembikhong bridge/129
Constn. of Retaining wall at Lembikhong Bridge at Sagolmang
09/02/2018
PWD
Imphal-East
18.00
0.00
State Plan
On going
1
24.951535088241833,94.02505489583973
Progress Update : 21/03/2018
On going
1
robin
24.951535088241833,94.02505489583973
24.95110494,94.02511597
0.048222662047313
0
State work

Progress Update : 21/03/2018
On going
1
robin
24.951535088241833,94.02505489583973
24.9510547,94.02514091
0.054113430873045
0
State work