Progress
 
 
Project Details
DAR-2018-000472
IED/Kiyamgei Bridge/123
Renovation/repairing work for Kiyamgei Bridge, Imphal East
2018-01-11
PWD
Imphal-East
26.38
11
State Plan
Completed
NA
24.74128393724544,93.94673245248418
Progress Update : 2018-12-24
Completed
NA
shibadatta
24.74128393724544,93.94673245248418
24.741220927415,93.946599865439
0.01511129064748
Approved
2019-02-04 07:56:29
ace3pwd
11
Bridge

Progress Update : 2018-03-17
Completed
NA
shibadatta
24.74128393724544,93.94673245248418
24.7414226,93.9469258
0.024878372506859
Approved
2018-03-21 08:38:11
ace3pwd
0
Bridge repairing

Progress Update : 2018-03-17
Completed
NA
shibadatta
24.74128393724544,93.94673245248418
24.7411088,93.9463309
0.044983745798914
Approved
2018-03-21 08:38:19
ace3pwd
0
Bridge repairing

Foundation & Inauguration
-
-
-

-
-
-