Progress
 
 
Project Details
DAR-2018-000439
BPR/Impvt. of Kokilbon../16.
Impvt. of Kokilbon- IVR, Thana- IVR, Dairy to Eco- IVR & left out College Lambi(SH: E/W.& GSB).
2018-01-15
PWD
Bishnupur
50.00
0.00
State Plan
Completed
Phase II
24.4840265713527,93.78317801219487
Progress Update : 2018-10-11
Completed
Phase II
lalit
24.4840265713527,93.78317801219487
24.4861988,93.7824033
0.25393276620526
Approved
2018-10-11 10:23:53
se3pwd
0
Road work

Progress Update : 2018-10-11
Completed
Phase II
lalit
24.4840265713527,93.78317801219487
24.4861988,93.7824033
0.25393276620526
Approved
2018-10-11 10:24:28
se3pwd
0
Road work

Progress Update : 2018-10-11
Completed
Phase II
lalit
24.4840265713527,93.78317801219487
24.4990004,93.7744633
1.8840309688785
Approved
2018-10-11 10:25:13
se3pwd
0
Road work

Progress Update : 2018-10-11
Completed
Phase II
lalit
24.4840265713527,93.78317801219487
24.4989567,93.7744885
1.8785436804718
Approved
2018-10-11 10:26:11
se3pwd
0
Road work

Foundation & Inauguration
-
-
-

-
-
-