Progress
 
 
Project Details
NH-III/MorTH/2016-17/14
Strengthening of the existing 2 lane including paved shoulder on NH-150 from Km. 412.000 to Km. 433.000. Job No. 150/MN/2016-17/14
25/10/2016
PWD
Bishnupur
8955.55
0.00
MorTH Govt. of India, ( Central)
24.432583,93.718708
Strengthening of the existing pavement by providing 200 mm thick WMM, 70 mm thick DBM & 30 mm thick BC & paved shoulder by providing 225 mm thick GSB, WBM 75 mm thick IRC Grade-II & 150 mm thick IRC Grade-III, 200 mm thick WMM, 70 mm thick DBM & 30 mm thick BC, Construction of 1.50 m & 3.00 m span RCC Slab Culvert, Widening of existing 1.00, 1.50, 2.00 & 3.00 m RCC Slab Culvert, Widening of existing Minor Bridges, Construction of Protection-work, Construction of RCC - M20 Drain with cover, Reconstruction of formation for depressed portion of road for a total length of 500 Rm.