Progress
 
 
Project Details
DAR-2026-000073
SE1/SteelTrussBridge/Maklang River/Kamjong
Constn of Steel Truss Brdg over Maklang river-60m span in betwn Kangpat & Kangkum on Nambisha to Bungdung rd to connect Kamjong& kasomkhullen,kamjong
2023-11-09
PWD
Kamjong
1349.86
0.00
NABARD
40 percent
Phase I
24.62408,94.452027
construction of bridge
Progress Update : 2026-04-24
40 percent
Phase I
so1brd
24.62408,94.452027
24.6244281,94.4513833
0.075705992849452
Approved
2026-06-04 11:07:23
se1pwd
0
abutment Shaft

Progress Update : 2026-04-24
40 Percent
Phase I
so1brd
24.62408,94.452027
24.6245457,94.4519523
0.05232862243433
Approved
2026-06-04 11:07:33
se1pwd
0
Abutment shaft

Progress Update : 2026-04-24
40 percent
Phase I
so1brd
24.62408,94.452027
24.6245569,94.4519853
0.053193577411914
Approved
2026-06-04 11:07:50
se1pwd
0
Abutment Shaft

Progress Update : 2026-03-13
40%
2nd phase
so1brd
24.62408,94.452027
24.6240467,94.4513667
0.066844515196891
Approved
2026-06-04 11:08:42
se1pwd
0
work in progress

Foundation & Inauguration
-
-
-

-
-
-