DAR-2026-000067
BD-I/Raj Bhavan/Staff Qtr/South Block
Construction of Staff Quarter Building at Raj Bhavan,Imphal-South Block
2025-10-27
PWD
Imphal-West
195.25
0.00
State Plan
32% completed
1
24.8033189,93.9366114
Constn.of staff quarter building including e/w,PCC,RCC,brick works,finishing works,sanitary works,etc
Progress Update : 2026-02-24
32% completed
1
7005049427
24.8033189,93.9366114
24.80235,93.9353917
0.16359002698193
Approved
2026-02-26 08:20:25
se2pwd
0
septic tank,land devlopment,dismantling,foundation

Progress Update : 2026-02-24
32% completed
1
7005049427
24.8033189,93.9366114
24.802656,93.935613
0.12485069387288
Approved
2026-02-26 08:20:34
se2pwd
0
Septic tank,land devlopment,dismantling,foundation.

Foundation & Inauguration
-
-
-

-
-
-