Progress
 
 
Project Details
DAR-2018-000321
TML/Road/CJM Court/4
Improvement of CJM road at District Head Quarter at Tamenglong
05/02/2016
PWD
Tamenglong
55.00
36.66
NABARD
completed
phase-2
24.989937415914117,93.50498025717809
Progress Update : 17/03/2018
completed
phase-2
eetmld
24.989937415914117,93.50498025717809
24.9920259,93.5023984
0.34875209358391
0
Name of work: Improvement of CJM Court approach road at Tamenglong Head Quarter. items of work: Kutcha line drain for 1.2 km, Shingling for 0.976km, WBM IRC geade - II & III for 1.2km and 2 cm P.C work has started

Progress Update : 17/03/2018
work in progress
phase-2
eetmld
24.989937415914117,93.50498025717809
24.989538,93.5053697
0.059268487016303
0
Name of work: Improvement of CJM Court approach road at Tamenglong Head Quarter. items of work: Kutcha line drain for 1.2 km, Shingling for 0.976km, WBM IRC geade - II & III for 1.2km and 2 cm P.C work has started

Progress Update : 17/03/2018
work in progress
phase-2
eetmld
24.989937415914117,93.50498025717809
24.9905201,93.500987
0.40762216625476
0
Name of work: Improvement of CJM Court approach road at Tamenglong Head Quarter. items of work: Kutcha line drain for 1.2 km, Shingling for 0.976km, WBM IRC geade - II & III for 1.2km and 2 cm P.C work has started

Progress Update : 17/03/2018
work in progress
phase-2
eetmld
24.989937415914117,93.50498025717809
24.9897685,93.505786
0.08334674864963
0
Name of work: Improvement of CJM Court approach road at Tamenglong Head Quarter. items of work: Kutcha line drain for 1.2 km, Shingling for 0.976km, WBM IRC geade - II & III for 1.2km and 2 cm P.C work has started

Progress Update : 17/03/2018
work in progress
phase-2
eetmld
24.989937415914117,93.50498025717809
24.9920259,93.5023984
0.34875209358391
0
Name of work: Improvement of CJM Court approach road at Tamenglong Head Quarter. items of work: Kutcha line drain for 1.2 km, Shingling for 0.976km, WBM IRC geade - II & III for 1.2km and 2 cm P.C work has started

Progress Update : 17/03/2018
work in progress
phase-2
eetmld
24.989937415914117,93.50498025717809
24.9903872,93.5064309
0.15451328845316
0
Name of work: Improvement of CJM Court approach road at Tamenglong Head Quarter. items of work: Kutcha line drain for 1.2 km, Shingling for 0.976km, WBM IRC geade - II & III for 1.2km and 2 cm P.C work has started

Progress Update : 17/03/2018
work in progress
phase-2
eetmld
24.989937415914117,93.50498025717809
24.9897685,93.505786
0.08334674864963
0
Name of work: Improvement of CJM Court approach road at Tamenglong Head Quarter. items of work: Kutcha line drain for 1.2 km, Shingling for 0.976km, WBM IRC geade - II & III for 1.2km and 2 cm P.C work has started

Progress Update : 17/03/2018
work in progress
phase-2
eetmld
24.989937415914117,93.50498025717809
24.9920259,93.5023984
0.34875209358391
0
Name of work: Improvement of CJM Court approach road at Tamenglong Head Quarter. items of work: Kutcha line drain for 1.2 km, Shingling for 0.976km, WBM IRC geade - II & III for 1.2km and 2 cm P.C work has started

Progress Update : 17/03/2018
work in progress
phase-2
eetmld
24.989937415914117,93.50498025717809
24.9920259,93.5023984
0.34875209358391
0
Name of work: Improvement of CJM Court approach road at Tamenglong Head Quarter. items of work: Kutcha line drain for 1.2 km, Shingling for 0.976km, WBM IRC geade - II & III for 1.2km and 2 cm P.C work has started