Progress
 
 
Project Details
DAR-2025-000442
EAP/Imphal Ringroad/02
Construction of Imphal Ring Road Project
09/11/2021
PWD
Imphal East & Imphal West
166000.00
15842.29
State Plan
1.41%
02
24.744550434147357,93.93585357070003
Construction of 51.23 km of roads in Imphal city with flexible pavement including effective drainage system out of which 17.50 km will be on green field alignment and the project execution includes road works, drains, retaining structures and culverts etc.
Progress Update : 15/10/2025
1.41%
02
Imphal ringroad
24.744550434147357,93.93585357070003
24.8181767,93.8809317
9.8872968067139
0
Installation of batching plant is done at camp location.

Progress Update : 14/10/2025
1.41%
phase-02
Imphal ringroad
24.744550434147357,93.93585357070003
24.8183301,93.8811183
9.8908860786333
0
Erection of RMC Plant is completed, construction of Laboratory in progress, setup of office and Engineers quarters is completed, Weigh bridge erection is completed, Mechanical workshop in progress, finalisation of land for erection of WMM Plant, Crusher, Hm plant is completed. Soil quarry and Rock quarry yet to operate and general requirements in progress.7 box culvert and 1 km of drain completed at site and earthwork excavation for retaining wall in progress.CNG work at greenfield is started.