Progress
 
 
Project Details
DAR-2018-000316
WP-15-SE(S)-HEIH/S-LD
Construction of Additional 6(Six) Classrooms of Heirok High School, Thoubal District. (SH: Ground Development)
2015-03-24
Education (S)
Thoubal
40.00
33.33
State Plan
Completed
Nil
24.587074756052814,94.0612074374344
Construction of Additional 6(Six) Classrooms of Heirok High School, Thoubal District. (SH: Land Development)
Progress Update : 2018-02-27
Completed
Nil
sur1.eew-mn
24.587074756052814,94.0612074374344
24.5871133,94.06144
0.023901250548426
Approved
2018-12-22 10:54:59
ce.eew-mn
0
Front view leveling

Progress Update : 2018-02-27
Completed
Nil
sur1.eew-mn
24.587074756052814,94.0612074374344
24.587115,94.0614217
0.022121100957958
Approved
2018-12-22 10:54:47
ce.eew-mn
0
Front view leveling

Foundation & Inauguration
-
-
-

-
-
-