Progress
 
 
Project Details
DAR-2018-000315
WRD-FCW-87
Improvement of Imphal River and improvement of Irong Nallah
2018-01-16
Water Resources Department (WRD)
Imphal-East
601.50
0.00
State Plan
Completed
Final phase
24.80748517734833,93.94173431396518
The project is created for improvement bund of these river at different locations by providing earthwork, bore piles, retaining walls etc.
Progress Update : 2018-06-12
Completed
Final phase
FCD-1
24.80748517734833,93.94173431396518
24.8922279,93.9389364
9.4267352582922
Approved
0
Bored pile with Rcc Retaining wall at Mongjam Konthoujam Mapa LBB for a length of 100 m

Progress Update : 2018-06-12
Completed
Final phase
FCD-1
24.80748517734833,93.94173431396518
24.8568816,93.9344545
5.541275681649
Approved
0
Bored pile with Rcc Retaining wall at Mongjam Mutum Mapa LBB for a length of of 80.00 m

Foundation & Inauguration
-
-
-

-
-
-