Progress
 
 
Project Details
DAR-2018-000311
MSPCLB13
Renovation and modernisation of 132 kV SS located at Kakching, Karong and Churachandpur phase II
2013-07-19
POWER (MSPCL)
Kakching
5498.59
4690.89
NLCPR
100%
Phase 2
24.47997854251247,94.01292320068364
Renovation and modernisation of 132 kV SS located at Kakching, Karong and Churachandpur phase II.
Progress Update : 2019-03-04
100%
Phase 2
tapan
24.47997854251247,94.01292320068364
24.3902888,93.7071046
32.52470908999
Approved
2019-03-08 11:54:47
davidkumar
0
O

Progress Update : 2019-03-04
95
A
sanajaoba
24.47997854251247,94.01292320068364
24.661099008642,94.000495198923
20.177882563038
Approved
2019-03-04 07:16:27
davidkumar
0
A

Foundation & Inauguration
-
-
-

-
-
-