Progress
 
 
Project Details
DAR-2025-000270
SS/D-IV/ B BOLJANG/UJB/5 ACR
Construction of Dilapidated building primary school under Samagra shiksha for the year 2023-2024 at B Boljang UJB School Kangpokpi,Manipur
29/08/2023
Education (S)
Bishnupur
68.85
0.00
CSS / CPS
The work has been complete upto roofing
2023-2024
24.971611414857286,94.13019318479459
Construction of Dilapidated building primary school under Samagra shiksha for the year 2023-2024 at B Boljang UJB School Kangpokpi,Manipur Sh i) Construction of 5 Calssroom ii) Construction of Toilet Block for Boys and Girls )
Progress Update : 16/06/2025
The work has been complete upto roofing
2023-2024
so9.eew
24.971611414857286,94.13019318479459
24.970922,94.1305539
0.084841309891256
0
construction of 5 classroom

Progress Update : 16/06/2025
The work has been complete upto roof beam
2023-2024
so9.eew
24.971611414857286,94.13019318479459
24.9708636,94.1304429
0.086875416029201
0
construction of 5 classroom

Progress Update : 16/06/2025
The work has been complete upto roofing
2023-2024
so9.eew
24.971611414857286,94.13019318479459
24.9709305,94.1305136
0.082311348495708
0
construction of 5 classroom

Progress Update : 16/06/2025
The work has been complete upto roof beam
2023-2024
so9.eew
24.971611414857286,94.13019318479459
24.9709739,94.1303051
0.071777049406755
0
construction of classrooms have been completed upto roof beam level