DAR-2025-000253
BRDG/Iril river Leitanpokpi/005
Construction of Bailey Bridge over Iril river at Leitanpokpi.
20/02/2024
PWD
Imphal-West
649.90
157.02
State Plan
On going
II
25.0009718,94.0269918
Construction Abutment Pile, Abutment and launching of Bailey Bridge.
Progress Update : 13/05/2025
On going
II
so1brd3
25.0009718,94.0269918
25.0012481,94.0262069
0.08485203743265
157.02
Foundation and Substructure Completed