Progress
 
 
Project Details
DAR-2025-000197
SS/D-2/UtlouJrHS BDRY- BSP
Construction of Boundary Wall with Gate (Rejuvenation Project) under Samagra Shiksha Manipur,2022-23 at Utlou Junior High School, Bishnupur, Manipur.
08/08/2023
Education (S)
Bishnupur
63.92
45.72
Samagra Shiksha
Completed
Nill
24.724197736359802,93.85821032524143
Construction of Boundary Wall with Gate (Rejuvenation Project) under Samagra Shiksha Manipur,2022-23 at Utlou Junior High School, Bishnupur, Manipur (Sh Construction of Boundary Wall Sh Construction of Gate)
Progress Update : 20/03/2025
Completed
Nill
so2.eew-mn
24.724197736359802,93.85821032524143
24.7169903,93.8589415
0.80478719868279
0
Front Gate

Progress Update : 20/03/2025
Completed
Nill
so2.eew-mn
24.724197736359802,93.85821032524143
24.7180384,93.8607146
0.73006770762036
0
Fencing View

Progress Update : 20/03/2025
Completed
Nill
so2.eew-mn
24.724197736359802,93.85821032524143
24.717471,93.8592775
0.7556693486081
0
Fencing View

Progress Update : 20/03/2025
Completed
Nill
so2.eew-mn
24.724197736359802,93.85821032524143
24.7175183,93.8594267
0.75277624232516
0
Fencing View