Progress
 
 
Project Details
DAR-2025-000195
SPT/Compound n renovation AE Office Mao/311
Constn of compound fencing and renovation of AE office at Mao
29/12/2023
PWD
Senapati
70.00
0.00
State Plan
57%
1
25.51203226896644,94.13626420497928
Contruction of compound fencing, retaining wall, renovation of building
Progress Update : 19/03/2025
57%
1
eesptd
25.51203226896644,94.13626420497928
25.5120921,94.1363486
0.010769095380527
0
compound fencing,office renovation

Progress Update : 19/03/2025
57%
1
eesptd
25.51203226896644,94.13626420497928
25.5119933,94.1359815
0.028697985349256
0
compound fencing,office renovation

Progress Update : 19/03/2025
57%
1
eesptd
25.51203226896644,94.13626420497928
25.5120792,94.1359833
0.028667037341109
0
compound fencing,office renovation