Progress
 
 
Project Details
DAR-2025-000188
EE/BPR/Constn of Upper Komkeirap
Construction of drain from Upper Komkeirap to Lower Komkeirap
2025-01-22
PWD
Bishnupur
100.00
0.00
State Plan
Ongoing27pc
phase 1
24.583523740375774,93.73432994893493
road work
Progress Update : 2025-03-19
Ongoing27pc
phase 1
lalit
24.583523740375774,93.73432994893493
24.5836317,93.7336968
0.065133965930444
Approved
2025-03-19 10:33:37
se3pwd
0
RCC CULVERT, RETAINING WALL, CC DRAIN ETC.

Foundation & Inauguration
-
-
-

-
-
-