Progress
 
 
Project Details
DAR-2025-000135
NNY/Nungnang to Ragailong village Taotiap/291
Impvt of road from Nungnang to Ragailong village via Taotiapduibong, Noney District
11/07/2024
PWD
Noney
164.83
0.00
State Plan
50%
2nd phase
24.71797,93.51587
Hill cutting & Kutcha drain
Progress Update : 20/03/2025
50%
2nd phase
eenoneyd
24.71797,93.51587
24.7240278,93.51822
0.71415918578022
0
hill cutting

Progress Update : 10/03/2025
50%
1st phase
eenoneyd
24.71797,93.51587
24.7175383,93.5177382
0.1947019795113
0
widdening and kutcha drain

Progress Update : 10/03/2025
25%
1st phase
eenoneyd
24.71797,93.51587
24.7173607,93.5179021
0.21613888688866
0
widdening and kutcha drain