Progress
 
 
Project Details
DAR-2025-000134
NNY/Kiangbianpang to Mongjarong/290
Impvt of road from Kiangbianpang to Mongjarong village, Noney District
2024-07-11
PWD
Noney
113.11
0.00
State Plan
50%
2nd phase
24.794933,93.479083
Hill cutting & Kutcha drain
Progress Update : 2025-03-20
50%
2nd phase
eenoneyd
24.794933,93.479083
24.8074054,93.4745079
1.4616641927035
Approved
2025-03-20 11:58:25
pwdse2ce
0
Hill cutting

Progress Update : 2025-03-10
25%
1st phase
eenoneyd
24.794933,93.479083
24.8089141,93.475535
1.5952676424501
Approved
2025-03-12 11:00:54
pwdse2ce
0
widdening

Progress Update : 2025-03-10
25%
1st phase
eenoneyd
24.794933,93.479083
24.8089312,93.475394
1.6003716909418
Approved
2025-03-12 11:01:08
pwdse2ce
0
widdening