Progress
 
 
Project Details
DAR-2025-000106
SS/D-2-ResidentialSL 2QTR- SPT
Construction of Residential Staff Quarter Under Samagra Shiksha, Manipur 2023-24 at Residential School, Senapati , Manipur.
31/08/2023
Education (S)
Senapati
48.86
0.00
Samagra Shiksha
Under Construction
Nill
25.52753330168727,93.92978775501285
Construction of Residential Staff Quarter Under Samagra Shiksha, Manipur 2023-24 at Residential School, Senapati , Manipur.(Sh Const of 2 Residential Staff Quarter Sh Const of 2 Septic Tank & Soak Pit)
Progress Update : 18/02/2025
Under Construction
Nill
so8.eew
25.52753330168727,93.92978775501285
25.5289617,93.9293108
0.16587601618447
0
Roof Top

Progress Update : 18/02/2025
Under Construction
Nill
so8.eew
25.52753330168727,93.92978775501285
25.5290068,93.9294928
0.16648904323484
0
Interior View

Progress Update : 18/02/2025
Under Construction
Nill
so8.eew
25.52753330168727,93.92978775501285
25.5288596,93.9294122
0.15220851240657
0
Side View

Progress Update : 18/02/2025
Under Construction
Nill
so8.eew
25.52753330168727,93.92978775501285
25.5289917,93.9295182
0.16439862065523
0
Front View