Progress
 
 
Project Details
DAR-2025-000084
COSFOM/RWH/CHOITHAR/VA COURT GUEST HOUSE
COSFOM/RWH/CHOITHAR/VA COURT GUEST HOUSE
2023-03-22
FOREST
Ukhrul
0.55
0.55
EAP
COMPLETED
NILL
25.0760812479653,94.39809608459507
Installation of 4000 litres of Roof top rain water harvesting structure at VA court Guest house of Choithar Village
Progress Update : 2025-02-01
COMPLETED
NILL
ENFOGAL
25.0760812479653,94.39809608459507
25.0760645,94.3979854
0.011301143638074
Approved
2025-02-04 10:01:07
dfoukhrul
0.55
FUNCTIONAL AND USED BY THE COMMUNITY

Progress Update : 2025-02-01
COMPLETED
NILL
ENFOGAL
25.0760812479653,94.39809608459507
25.0760512,94.3980278
0.0076453134404643
Approved
2025-02-04 10:01:22
dfoukhrul
0.55
FUNCTIONAL AND USED BY THE COMMUNITY

Foundation & Inauguration
-
-
-

-
-
-