Progress
 
 
Project Details
DAR-2024-001171
COSFOM/RWH/SHANGSHAK/RESIDENTIAL SCHOOL
COSFOM/RWH/SHANGSHAK/RESIDENTIAL SCHOOL
22/03/2023
FOREST
Ukhrul
0.55
0.55
EAP
Completed
Nil
25.007432704857575,94.33681833744083
Installation of 4000 liters of Roof top rain water harvesting structure at the Residential School of Shangshak Phunghon
Progress Update : 09/02/2025
Completed
Nil
dfoukhrul
25.007432704857575,94.33681833744083
25.009405,94.3447033
0.82423780561249
0.55
Operational and use by the community

Progress Update : 09/02/2025
Completed
Nil
dfoukhrul
25.007432704857575,94.33681833744083
25.009425,94.34454
0.80899386585497
0.55
Operational and use by the community