Progress
 
 
Project Details
DAR-2024-001128
SS/23-D3/HiyanglamMayaiIbetombiPS(Dila)-KAK
Construction of Dilapidated Building Primary School for the year 2023-2024 at Hiyanglam Mayai Ibetombi Primary School, Kakching, Manipur.
2023-08-29
Education (S)
Kakching
81.24
75.45
CSS / CPS
completed
final
24.51806596676276,93.92548170919267
Construction of Dilapidated Building Primary School for the year 2023-2024 at Hiyanglam Mayai Ibetombi Primary School, Kakching, Manipur. 1) SH. Construction of 5(five) Classrooms. 2) SH. Construction of Toilet for Boys & Girls.
Progress Update : 2025-10-06
completed
final
ae.elect-eew
24.51806596676276,93.92548170919267
24.5180838,93.9255041
0.0030109657360503
Approved
2025-12-16 10:37:01
ee3@eew
0
Full view of Classroom

Progress Update : 2025-10-06
completed
final
so11.eew
24.51806596676276,93.92548170919267
24.5177229,93.9255824
0.039482169022964
Approved
2025-12-16 10:37:50
ee3@eew
0
Front view of Classroom - main

Progress Update : 2025-10-06
Completed
final
ae.elect-eew
24.51806596676276,93.92548170919267
24.51822,93.925515
0.017454867759411
Approved
2026-01-05 10:26:49
ee3@eew
0
IEI for Toilet

Progress Update : 2025-10-06
completed
final
so11.eew
24.51806596676276,93.92548170919267
24.51775,93.9254847
0.03513360559157
Approved
2025-12-16 11:08:39
ee3@eew
0
Inside view of classroom

Progress Update : 2025-10-06
completed
final
so11.eew
24.51806596676276,93.92548170919267
24.5178255,93.9255328
0.02723238207909
Approved
2025-12-16 11:09:19
ee3@eew
0
Front view of L-shape classroom

Progress Update : 2025-10-06
completed
Final
so11.eew
24.51806596676276,93.92548170919267
24.5177332,93.9254856
0.037002167323289
Approved
2025-12-16 11:10:06
ee3@eew
0
Inner view of Toilet

Progress Update : 2025-10-06
completed
final
so11.eew
24.51806596676276,93.92548170919267
24.5177798,93.9255433
0.032423118167643
Approved
2025-12-16 10:38:38
ee3@eew
0
front view of Toilet

Progress Update : 2025-10-06
Completed
final
ae.elect-eew
24.51806596676276,93.92548170919267
24.5180899,93.925433
0.00560010854673
Approved
2026-01-05 10:25:38
ee3@eew
0
IEI for classroom

Progress Update : 2025-10-06
completed
final
ae.elect-eew
24.51806596676276,93.92548170919267
24.5181218,93.9254383
0.007605130652264
Approved
2026-01-05 10:24:33
ee3@eew
0
IEI for classroom

Progress Update : 2025-04-15
in progress
2nd
so11.eew
24.51806596676276,93.92548170919267
24.5177958,93.9252608
0.037440877498193
Approved
2025-04-22 08:45:59
ee3@eew
0
Verandah of Classroom

Progress Update : 2025-04-15
in progress
2nd
so11.eew
24.51806596676276,93.92548170919267
24.5177774,93.9252771
0.038182928881177
Approved
2025-04-22 08:45:43
ee3@eew
0
Toilet front

Progress Update : 2025-04-15
in progress
2nd
so11.eew
24.51806596676276,93.92548170919267
24.5177964,93.9252693
0.036879825209561
Approved
2025-04-22 08:45:09
ee3@eew
0
front view of classroom with boys toilet

Progress Update : 2025-04-15
in progress
2nd
so11.eew
24.51806596676276,93.92548170919267
24.5177793,93.9252672
0.038560227066741
Approved
2025-04-22 08:44:20
ee3@eew
0
front view of classroom

Progress Update : 2025-04-15
in progress
2nd
so11.eew
24.51806596676276,93.92548170919267
24.517797,93.9252648
0.037093142838469
Approved
2025-04-22 08:43:54
ee3@eew
0
Inner view of classroom

Progress Update : 2024-11-15
in progress
1st RA
so11.eew
24.51806596676276,93.92548170919267
24.5180883,93.9256592
0.018126550078026
Approved
2024-11-29 06:22:13
ee3@eew
0
Toilet

Progress Update : 2024-11-15
in progress
1st RA
so11.eew
24.51806596676276,93.92548170919267
24.5180878,93.9256582
0.01801909301654
Approved
2024-11-29 06:24:01
ee3@eew
0
inner view

Progress Update : 2024-11-15
in progress
1st RA
so11.eew
24.51806596676276,93.92548170919267
24.5180728,93.9256931
0.021398616433417
Approved
2024-11-29 06:23:39
ee3@eew
0
verandah portion

Progress Update : 2024-11-15
in progreas
1st RA
so11.eew
24.51806596676276,93.92548170919267
24.5180749,93.9256748
0.0195591864031
Approved
2024-11-29 06:23:06
ee3@eew
0
front view

Foundation & Inauguration
-
-
-

-
-
-