Progress
 
 
Project Details
DAR-2018-000260
NEC-Top Dusara
Augmentation of Top Dusara water supply scheme
2017-04-25
PHED
Imphal-East
504.93
0.00
NEC
in progress
I
24.813547436913854,93.98769664764427
Construction of WTP
Progress Update : 2018-08-25
in progress
I
romen
24.813547436913854,93.98769664764427
24.8278569,93.9819433
1.6936944354284
Approved
2018-08-30 08:07:48
eeiephed
0
Casting of Settling tank wall

Progress Update : 2018-08-24
in progress
I
romen
24.813547436913854,93.98769664764427
24.8121516,93.9876832
0.15520843490007
Approved
2018-08-30 08:07:02
eeiephed
0
Fencing gate

Progress Update : 2018-08-14
in progress
I
romen
24.813547436913854,93.98769664764427
24.817867,93.9816245
0.77860354199119
Approved
2018-08-30 08:05:43
eeiephed
0
Casting of Settling tank wall

Progress Update : 2018-07-27
in progress
I
romen
24.813547436913854,93.98769664764427
24.8135059,93.9877017
0.0046467598679648
Approved
2018-08-30 08:04:51
eeiephed
0
Casting of wall of Settling tank

Progress Update : 2018-06-06
in progress
I
romen
24.813547436913854,93.98769664764427
24.8134237,93.9875349
0.021348863908284
Approved
2018-08-30 08:01:36
eeiephed
0
Casting of rcc base slab of Settling tank

Progress Update : 2018-06-03
in progress
I
romen
24.813547436913854,93.98769664764427
24.818212,93.9825811
0.73180403907621
Approved
2018-08-30 08:00:47
eeiephed
0
Reinforcement of Settling tank

Progress Update : 2018-05-28
in progress
I
romen
24.813547436913854,93.98769664764427
24.8131833,93.9879103
0.045872077099277
Approved
2018-08-30 07:59:07
eeiephed
0
Reinforcement of Settling tank

Progress Update : 2018-05-24
in progress
I
romen
24.813547436913854,93.98769664764427
24.8186584,93.9797113
0.98611500169745
Approved
2018-08-30 07:58:16
eeiephed
0
Reinforcement of base plate of Settling tank

Progress Update : 2018-04-19
in progress
I
romen
24.813547436913854,93.98769664764427
24.8135363,93.9879467
0.025266737276786
Approved
2018-08-30 07:56:15
eeiephed
0
Construction of service reservoir-earthwork

Progress Update : 2018-04-08
in progress
I
romen
24.813547436913854,93.98769664764427
24.8131375,93.978436
0.93573731132736
Approved
2018-08-30 07:55:50
eeiephed
0
Excavation for settling tank

Progress Update : 2018-04-05
in progress
I
romen
24.813547436913854,93.98769664764427
24.8131375,93.978436
0.93573731132736
Approved
2018-08-30 07:54:54
eeiephed
0
Fencing at southern side

Progress Update : 2018-03-23
in progress
I
romen
24.813547436913854,93.98769664764427
24.8058321,93.9831592
0.97244724162
Approved
2018-08-30 07:53:57
eeiephed
0
Construction of fencing

Progress Update : 2018-03-19
in progress
I
romen
24.813547436913854,93.98769664764427
24.8135807,93.9887291
0.10426519197307
Approved
2018-08-30 07:51:49
eeiephed
0
Construction of fencing

Progress Update : 2018-03-19
in progress
I
romen
24.813547436913854,93.98769664764427
24.8057884,93.9902344
0.89994158392613
Approved
2018-08-30 07:50:04
eeiephed
0
Construction of fencing

Foundation & Inauguration
-
-
-

-
-
-