DAR-2024-001116
SE-I/DAR/20-21/CRIF/IE-R1.31 NH39 - Irilbung
Improvement of road from NH-39 to Irilbung via Kongba Irong
2020-10-29
PWD
Imphal-East
2335.88
656.37
CSS / CPS
in progress
NA
24.754965,93.944505
Impvt of Road, Drain PW
Progress Update : 2025-08-20
in progress
NA
shibadatta
24.754965,93.944505
24.7496224,93.9717977
2.8191559509113
Approved
2025-08-22 07:48:45
se1pwd
656.37
road

Progress Update : 2025-08-20
in progress
NA
shibadatta
24.754965,93.944505
24.7502807,93.9769865
3.3208833609795
Approved
2025-08-22 07:49:15
se1pwd
656.37
road

Progress Update : 2024-10-15
In progress 40 pc
---
shibadatta
24.754965,93.944505
24.7526489,93.9429035
0.3040876100271
Approved
2025-02-13 11:31:10
se1pwd
596.37
Road work - BT work in progress

Progress Update : 2024-10-15
In progress
NA
shibadatta
24.754965,93.944505
24.754965,93.944105
0.040388758759101
Approved
0
Impvt of Road - BT work in progress

Foundation & Inauguration
-
-
-

-
-
-