Progress
 
 
Project Details
DAR-2018-000242
IWD/Patsoi Lamkhai-Sangaithel/33
Impvt. of Sagolband Maklang Road from Patsoi Lamkhai to Sangaithel.
09/02/2018
PWD
Imphal-West
260.00
0.00
State Plan
Completed
1
24.803501940985154,93.85192322731041
Progress Update : 17/04/2018
Completed
1
thengra
24.803501940985154,93.85192322731041
24.8039409,93.8510618
0.099708453721615
0
GSB,WBM,sdbc

Progress Update : 23/02/2018
In progress
Phase 1
thengra
24.803501940985154,93.85192322731041
24.800161,93.8648001
1.3517580025629
0
Wbm 2nd layer

Progress Update : 23/02/2018
In progress
Phase 1
thengra
24.803501940985154,93.85192322731041
24.8001346,93.8648194
1.354439769204
0
Wbm 2nd layer

Progress Update : 23/02/2018
In progress
Phase 1
thengra
24.803501940985154,93.85192322731041
24.7997097,93.8687306
1.748054073068
0
Wbm 2nd layer

Progress Update : 15/02/2018
In progress
Phase
thengra
24.803501940985154,93.85192322731041
24.8084545,93.9334533
8.2472779024012
0
WbmIII