Project Lists

Showing 201-220 of 670 items.
#CodeNameDepartmentDistrictApproved Project Cost (in Lakhs)Fund Utilized so far(in Lakhs)Source of FundingPhysical ProgressFinancial ProgressSectorCreate DateFinancial YearProject Start DateStatus
      
 
201MID-IV-PMKSY-NNY-03-2020-21-Kekhru NagaConstruction of Irrigation Tank at Tajeikaiphun, Kekhru Naga, Noney.Minor Irrigation DepartmentNoney100.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
202MID-IV-PMKSY-NNY-02-2020-21-LongmaiConstruction of Irrigation Tank at Longmai, Noney.Minor Irrigation DepartmentNoney100.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
203MID-IV-PMKSY-TML-20-2020-21-TamahConstn. of Irrigation Tank at Tamah Village.Minor Irrigation DepartmentTamenglong40.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
204MID-IV-PMKSY-TML-20-2020-21-TamahConstn. of Irrigation Tank at Tamah Village.Minor Irrigation DepartmentTamenglong40.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
205MID-IV-PMKSY-TML-19-2020-21-TajiangningConstn.of P/W & I.C. a/c Kajingrua River at Tajiangning Village.Minor Irrigation DepartmentTamenglong50.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
206MID-IV-PMKSY-TML-18-2020-21-KawalungConstn.of P/W & I.C. a/c Apuakki River at Kawalung.Minor Irrigation DepartmentTamenglong50.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
207MID-IV-PMKSY-TML-17-2020-21-KhunphungConstn. ofP/W & I.C. a/c Agaki River at Khunphung.Minor Irrigation DepartmentTamenglong55.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
208MID-IV-PMKSY-TML-16-2020-21-ThadaithuakConstn.of P/W & I.C. a/c Thadaithuak river at Thangal Village.Minor Irrigation DepartmentTamenglong50.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
209MID-IV-PMKSY-TML-15-2020-21-KahulongConstruction of P/W & I.C. a/c Duinang stream at Kahulong Village.Minor Irrigation DepartmentTamenglong40.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
210MID-IV-PMKSY-TML-15-2020-21-KahulongConstruction of P/W & I.C. a/c Duinang stream at Kahulong Village.Minor Irrigation DepartmentTamenglong40.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
211MID-IV-PMKSY-TML-14-2020-21-KhanchiuluanConstructionof P/W & I.C. a/c Duikhunpang stream at Khanchiuluan village .Minor Irrigation DepartmentTamenglong50.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
212MID-IV-PMKSY-KMJ-13-2020-21-ChatonConstructionof Irrigation Tank at Chaton Village.Minor Irrigation DepartmentTamenglong50.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
213MID-IV-PMKSY-TML-12-2020-21-NazarethConstructionof Irrigation Tank Irrigation at Nazareth of Kahulong village.Minor Irrigation DepartmentTamenglong30.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
214MID-IV-PMKSY-TML-11-2020-21-DailongConstructionof Irrigation Tank at Dailong village.Minor Irrigation DepartmentTamenglong30.000.00CSS / CPS23/02/20212019-2020-In-ProgressView
215MID-IV-PMKSY-TML-10-2020-21-ThengjangConstructionof Irrigation Tank at Thengjang village.Minor Irrigation DepartmentTamenglong30.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
216MID-IV-PMKSY-TML-09-2020-21-Old KaiphundailConstructionof P/W & I.C. a/c Old Kaiphundai Quarry stream at Old Kaiphundail Village.Minor Irrigation DepartmentTamenglong30.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
217MID-IV-PMKSY-TML-08-2020-21-Old PallongConstructionof P/W & I.C. a/c Ruaitajei stream at Old Pallong Village.Minor Irrigation DepartmentTamenglong30.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
218MID-IV-PMKSY-TML-07-2020-21-KhebuchingConstn.of P/W & I.C. a/c Duilangdai stream at Khebuching.Minor Irrigation DepartmentTamenglong65.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
219MID-IV-PMKSY-TML-06-2020-21-Hutanang LoukolConstn.of P/W & I.C. a/c Appa river at Lower Sonpram Hutanang LoukolMinor Irrigation DepartmentTamenglong70.000.00CSS / CPS23/02/20212020-2021-In-ProgressView
220MID-IV-PMKSY-TML-05-2020-21-GuankaijangConstn.of Regulator & I.C. at Guankaijang.Minor Irrigation DepartmentTamenglong40.000.00CSS / CPS23/02/20212020-2021-In-ProgressView