| 201 | BD-III/AE-V/BIR TIKENDRAJIT HOUSE Main. | Addition and Alteration of Bir Tikendrajit House Chanakyapuri New Delhi(SH:-Main Building) | PWD | Others | 3 | 100 | 14/10/2024 |
| 202 | BD-II/AE-III/Qtr.No.15 Ex-CM | Renovation of Qtr.No.15 at Babupara.(Ex-CM) | PWD | Imphal-West | I | 100 | 05/02/2025 |
| 203 | BD-II/AE-III/Beautification Sanjenthong | Beautification and steel grill fencing at Sanjenthong Officer Colony | PWD | Imphal-East | 2 | 100 | 05/03/2021 |
| 204 | BD-II/AE-III/Children park at Sanjenthong | Impvt.of Children Park at Sanjenthong | PWD | Imphal-East | 2 | 100 | 20/02/2025 |
| 205 | MSPCLC5 | Installation of 2x5 MVA, 33/11 kV Sub-Station with associated 33 kV line at Nungbi Khullen | POWER (MSPCL) | Ukhrul | X | 100 | 15/03/2018 |
| 206 | TBL/Darpan/Deposit Work/48 | Restoration of State District & Village road damaged during from 2015/restoration of roads damaged during flood 2015 in the Thoubal District | PWD | Kakching | Phase III | 100 % | 14/01/2020 |
| 207 | IWD/Shantipur Driver colony-Premnagar/117 | Impvt. of Shantipur to Driver Colony Co-Operative to Prem Nagar IVR | PWD | Imphal-West | NA | 100 % | 27/06/2024 |
| 208 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 100 % | 21/01/2020 |
| 209 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 100 % | |
| 210 | TBL/Darpan/Deposit Work/48 | Restoration of State District & Village road damaged during from 2015/restoration of roads damaged during flood 2015 in the Thoubal District | PWD | Kakching | Phase III | 100 % | 16/01/2020 |
| 211 | SE-I/IW/DRP/2023-24/R1/133-23 Konthoujam Lai | Improvement of road from Konthoujam Lairembi to Konthoujam Makha via Nongraobung | PWD | Imphal-West | Nil | 100 % | 25/06/2024 |
| 212 | MSPCLA3 | Contruction of 2 nos. of 400 kV line bay at Imphal Power Grid Sub-Station, Yurembam | POWER (MSPCL) | Imphal-West | Xyz | 100 % | |
| 213 | IED/Huilap IVR/823 | Impvt. of Huikap IVR | PWD | Imphal-East | N/A | 100 % | 26/06/2024 |
| 214 | TBL/Darpan/Deposit Work/48 | Restoration of State District & Village road damaged during from 2015/restoration of roads damaged during flood 2015 in the Thoubal District | PWD | Kakching | Phase III | 100 % | 16/01/2020 |
| 215 | IED/Yairipok Thongkhong-Kuthabi IVR/821 | Impvt. of road from Yairipok Thongkhong to Kuthabi IVR | PWD | Imphal-East | N/A | 100 % | 26/06/2024 |
| 216 | MSPCLC4 | Installation of 2x2.5 MVA, 33/11 kV Sub-Station at Kasom Khullen with associated 33 kV line and related civil work | POWER (MSPCL) | Ukhrul | Completed | 100 % | 28/10/2020 |
| 217 | SPT/Kayinu to Mao Ring road/62 | Improvement of Kayinu to Mao Ring road via ICCP - 4.50 km | PWD | Senapati | Phase 1 | 100 % | 15/03/2023 |
| 218 | SPT/Kayinu to Mao Ring road/62 | Improvement of Kayinu to Mao Ring road via ICCP - 4.50 km | PWD | Senapati | Phase 1 | 100 % | |
| 219 | H&SC/NEC-REMF | Re-establishment of Magfruit Factory | Horticulture & Soil Conservation | Imphal-East | 2nd instalment | 100 % | 16/02/2019 |
| 220 | UKL/Nungbi Khullen/54 | Improvement of Nungbi Khullen IVR 0.00 to 1.50 km. | PWD | Ukhrul | Phase 3 | 100 % | 14/02/2023 |