| 181 | MSPCLB3 | INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORK | POWER (MSPCL) | Chandel | X | 100% | 25/10/2018 |
| 182 | MSPCLC50 | Installation of 2x5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Khongjaron, Tamenglong District on turn key ba | POWER (MSPCL) | Tamenglong | x | 70 | 08/09/2025 |
| 183 | MSPCLC1 | Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, Manipur | POWER (MSPCL) | Senapati | X | 100% | 02/03/2019 |
| 184 | MSPCLC1 | Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, Manipur | POWER (MSPCL) | Senapati | X | 100% | |
| 185 | MSPCLB3 | INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORK | POWER (MSPCL) | Chandel | X | 70% | 30/11/2017 |
| 186 | MSPCLB3 | INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORK | POWER (MSPCL) | Chandel | X | 70% | 30/11/2017 |
| 187 | MSPCLC35 | Re-stringing & strengthening of 33 kV line from Jiribam to Oinamlong on turn-key basis | POWER (MSPCL) | Jiribam | X | 50% | 13/02/2020 |
| 188 | MSPCLC49 | Installation of 2x5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Gwakhal, Jiribam District on turn key basis | POWER (MSPCL) | Jiribam | x | 70% | |
| 189 | MSPCLC1 | Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, Manipur | POWER (MSPCL) | Senapati | X | 90% | 20/12/2017 |
| 190 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 75% | 20/12/2017 |
| 191 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 75% | 20/12/2017 |
| 192 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 75% | 20/12/2017 |
| 193 | MSPCLC47 | Installation of 2x5 MVA 33/11 kV substation along with the associated 33 kV line and related civil works at Oinam, Senapati District on turn key basis | POWER (MSPCL) | Senapati | x | 85 | 08/09/2025 |
| 194 | MSPCLC47 | Installation of 2x5 MVA 33/11 kV substation along with the associated 33 kV line and related civil works at Oinam, Senapati District on turn key basis | POWER (MSPCL) | Senapati | X | 40 % | 24/08/2022 |
| 195 | MSPCLC40 | Installation of 2x5 MVA, 33/11 kV SS along with associated 33 kV line & related civil works at Joujangtek, Noney District on turn key basis | POWER (MSPCL) | Noney | x | 60 | 01/03/2025 |
| 196 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 100 % | |
| 197 | MSPCLB8 | Augmentation of Rengpang 132/33 kV SS by installing 132/33 kV Single Phase transformer | POWER (MSPCL) | Tamenglong | X | 85 | 21/12/2019 |
| 198 | MSPCLB8 | Augmentation of Rengpang 132/33 kV SS by installing 132/33 kV Single Phase transformer | POWER (MSPCL) | Tamenglong | X | 85 | 21/12/2019 |
| 199 | MSPCLC9 | Installation of 2x2.5 MVA 33/11 KV Sub-station along with the associated 33 KV line & related work at Gelnel | POWER (MSPCL) | Kangpokpi | X | 100 percent Completed | 23/02/2018 |
| 200 | MSPCLB6 | INSTALLATION OF 2x20 MVA, 132/33 kV S/S ALONG WITH ASSOCIATED 132 kV LILO LINE AND RELATED CIVIL WORKS AT ELANGKHANGPOKPI IN MANIPUR | POWER (MSPCL) | Kakching | X | 100 | 24/02/2018 |