161EE/ED-II/SDO-SDC/52Repairing of IEI i/c compound lighting in SDO, SDC, Registrar office (replacement of LED light) at Porompat, I E District PWDImphal-East1Completed2020-03-12 09:14:12
162UKL/Nungshong/65Impvt. of road (shingling & side drainage) from NH-150 Dungrei to Nungshong via Seipaikong 6th MR Bn. HQ & Tasar Oak farm (14 kms)PWDUkhrul1Ongoing2021-03-09 08:39:40
163WRD-FCW-150Flood Control Project under State Plan 2020-21(880 lakh)Water Resources Department (WRD)Others1Complete2021-03-05 07:31:02
16426/59/2017-W(NP)/BD1/NewSecttWB/1Renovation of room No. 120,122 & 101 alloted to Hon'ble Minister Shri Th. Biswajit Singh at Western Block 1st floor New Sectt.PWDImphal-West1Completed2017-07-03 06:47:33
165TBL/Darpan/plan/13Impt. of Sabaltongba Road-3.00kmPWDThoubal150%2018-03-14 11:37:00
16603Construction/upgradation of roads in Wangjing Lamding Nagar PanchayatMAHUDThoubal1Ongoing2018-04-17 07:11:02
167CDL/Impvt. of Hospital Rd. at Moreh/17.Impvt. of Hospital Rd. at Moreh.PWDChandel1Impvt of hospital road moreh
168NEC(Oklong)Composite Water Supply at OklongPHEDSenapati1new2018-12-20 08:31:38
169MQCD/Darpan/Luwangsangbam/PM/2018-19/35Preparation of Infrastructures in connection with the Inauguration & laying of Foundation Stones by the P.M of India at Luwangpokpa Cricket Stadium.PWDImphal-East1Completed2019-01-03 07:42:45
170EE/ED-II/SDO-SDC/52Repairing of IEI i/c compound lighting in SDO, SDC, Registrar office (replacement of LED light) at Porompat, I E District PWDImphal-East1Completed2020-03-12 09:13:49
171MSPCLC30Installation of 2x2.5 MVA, 33/11 kV SS along with associated 33 kV LILO line & related civil works at Paoyi, Ukhrul District.POWER (MSPCL)Ukhrul155%
172CSCBPR Phougakchao IkhaiConstruction of CSC at Phougakchao IkhaiPHEDBishnupur1Completed2020-12-08 10:07:01
173UKL/Nungshong/65Impvt. of road (shingling & side drainage) from NH-150 Dungrei to Nungshong via Seipaikong 6th MR Bn. HQ & Tasar Oak farm (14 kms)PWDUkhrul1Ongoing2021-03-09 08:40:15
17426/59/2017-W(NP)/BD1/NewSecttWB/1Renovation of room No. 120,122 & 101 alloted to Hon'ble Minister Shri Th. Biswajit Singh at Western Block 1st floor New Sectt.PWDImphal-West1Completed2017-07-03 06:46:58
175CDL/Impvt. of Rd.from Sita Lamkhai/12Impvt. of road from Sita Lamkhai to Wapurmancham.PWDChandel1completed2018-11-17 09:08:51
17603Construction/upgradation of roads in Wangjing Lamding Nagar PanchayatMAHUDThoubal1Ongoing2018-04-17 07:28:21
177CDL/Impvt. of Hospital Rd. at Moreh/17.Impvt. of Hospital Rd. at Moreh.PWDChandel1Impvt of hospital road moreh
178WSM-II-CHINGKHEICHINGConstruction of Water Treatment Plant at Chingkheiching (45.00 MLD Capacity) for Imphal CityPHEDImphal-East1Active2019-05-15 08:12:54
179EE/ED-II/SDO-SDC/52Repairing of IEI i/c compound lighting in SDO, SDC, Registrar office (replacement of LED light) at Porompat, I E District PWDImphal-East1Completed2020-03-12 09:13:27
180IED/RCCslab culvet- Laipham-Kabui/441Contrn. of 1.5m span RCC slab culvert at Laipham Khunou and 2.00 m RCC slab culvert near Kabui khulPWDImphal-East1state work2020-11-24 08:33:40