Progress

 
 
Project Details
DAR-2020-000370
AKAMPAT/Western Gallery
Construction of Mini Sports Complex at Akampat SEYO Club Ground, Imphal East,Manipur(SH:Constn. of Hockey VIP Western Gallery,Phase-I)
30/06/2018
PWD
Imphal-East
2000.00
500
MH:8443-CD Deposit Works
Completed
II
24.780432837368206,93.94709149259033
Const. of Hockey VIP Gallery, Phase-I,etc.
Progress Update : 08/11/2021
Completed
II
7085969655
24.780432837368206,93.94709149259033
24.7811355,93.946675
0.088723827021113
500
RCC Isolated footings, RCC columns, Racker beams, RCC slab, and gallery steps, brick walls, tiles flooring etc

Progress Update : 08/11/2021
Completed
II
7085969655
24.780432837368206,93.94709149259033
24.7809441,93.9471378
0.057038914379123
500
RCC Isolated footings, RCC columns, Racker beams, RCC slab, and gallery steps, brick walls, tiles flooring etc

Progress Update : 08/11/2021
Completed
II
7085969655
24.780432837368206,93.94709149259033
24.7809505,93.9470267
0.057929062218331
500
RCC Isolated footings, RCC columns, Racker beams, RCC slab, and gallery steps, brick walls, tiles flooring etc

Progress Update : 28/10/2020
70%
II
7085969655
24.780432837368206,93.94709149259033
24.7805288,93.9467412
0.036937204468946
122.93
Racket beams, slab and RCC steps for gallery, parapet wall etc

Progress Update : 28/10/2020
70%
II
7085969655
24.780432837368206,93.94709149259033
24.78112322,93.9467559
0.083906844921679
122.93
Racket beams, slab and RCC steps for gallery, parapet wall etc

Progress Update : 28/10/2020
70%
II
7085969655
24.780432837368206,93.94709149259033
24.7832736,93.945287
0.36462749024146
122.93
Racket beams, slab and RCC steps for gallery, parapet wall etc

Progress Update : 17/06/2020
In progress
1
7085969655
24.780432837368206,93.94709149259033
24.78041789,93.94697059
0.012317605241453
223.5
Laying of sand piles, footings, pedestals, grade beams, plinth beams, columns, reinforcement for racker beams etc

Progress Update : 16/06/2020
In progress
1
7085969655
24.780432837368206,93.94709149259033
24.78066466,93.9469612
0.028938306217236
223.5
Laying of sand piles, foundation, grade beams, plinth beams, columns, reinforcement of racker beams etc

Progress Update : 16/06/2020
In progress
1
7085969655
24.780432837368206,93.94709149259033
24.78064019,93.94694847
0.027203245196623
223.5
Laying of sand piles, foundation, grade beams, plinth beams, columns, reinforcement of racker beams etc

Progress Update : 19/03/2020
In progress
I
7085969655
24.780432837368206,93.94709149259033
24.7817754,93.9459243
0.19017854974617
223.5
Laying of sand pile, base plate, pedestal, filling available excavated earth etc

Progress Update : 19/03/2020
In progress
I
7085969655
24.780432837368206,93.94709149259033
24.78064052,93.94723064
0.027029097971124
223.5
Laying of sand pile, base plate, pedestal, filling available excavated earth etc

Progress Update : 18/03/2020
In progress
Phase-I
7085969655
24.780432837368206,93.94709149259033
24.78114294,93.9467284
0.08704946118677
223.5
Casting of base plate, pedastal, filling of earth etc.

Progress Update : 18/03/2020
In progress
Phase-I
7085969655
24.780432837368206,93.94709149259033
24.78051711,93.94676293
0.03446704616007
223.5
Casting of base plate, pedastal, filling of earth etc.