Progress

 
 
Project Details
CCP/Mini-Sectt
Construction of Mini Secretariat Churachandpur
2011-02-25
PWD
Churachandpur
5677.36
4166.2
State Plan
Completed
2015-18
24.3617044,93.7031143
The Project comprise of construction of 4(four) District Level Office (DLO), Single/Double Room Transit Hostels, Multipurpose Hall, Security Barracks and Tower, Compund Wall and Approach Road etc.
Progress Update : 2021-09-04
Completed
2015-18
soccpr1
24.3617044,93.7031143
24.362473333333,93.705601666667
0.26605430908532
4166.2
Building

Progress Update : 2021-09-04
Completed
2015-18
soccpr1
24.3617044,93.7031143
24.362473333333,93.705601666667
0.26605430908532
0
Building

Progress Update : 2020-10-29
On going work
2011
soccpr1
24.3617044,93.7031143
24.3613183,93.7043272
0.13013871002797
0
Building

Progress Update : 2020-10-29
On going work
2011
soccpr1
24.3617044,93.7031143
24.3613183,93.7043272
0.13013871002797
0
Building

Progress Update : 2020-09-10
Completed
2019_20
soccpr1
24.3617044,93.7031143
24.3623691,93.7068644
0.3869671419974
4156.2
Land scape

Progress Update : 2020-09-10
On going work
2019_20
soccpr1
24.3617044,93.7031143
24.3627708,93.7055958
0.27791243351739
0
Garrage

Progress Update : 2020-01-25
In progress
2013-14
soccpr1
24.3617044,93.7031143
24.36281,93.705706666667
0.28992945466319
0
Building

Progress Update : 2018-10-11
On going work
1
soccpr1
24.3617044,93.7031143
24.3567103,93.7037642
0.55918024001706
0
Building

Progress Update : 2017-07-13
On going
1
soccpr1
24.3617044,93.7031143
24.3635823,93.706453
0.39744031207948
0
Rcc work, wood work, grill

Progress Update : 2017-07-13
On going
1
soccpr1
24.3617044,93.7031143
24.3626157,93.7048085
0.19928610447727
0
Rcc work, wood work, grill

Progress Update : 2017-07-13
On going
1
soccpr1
24.3617044,93.7031143
24.3628525,93.7059138
0.31096832541606
0
Rcc work, wood work, grill

Progress Update : 2017-07-13
On going
1
soccpr1
24.3617044,93.7031143
24.3628764,93.7059672
0.31699133598646
0
Rcc work, wood work, grill

Progress Update : 2017-07-13
On going
1
soccpr1
24.3617044,93.7031143
24.36326,93.7062089
0.3580039738259
0
Rcc work, wood work, grill

Progress Update : 2017-07-13
On going
1
soccpr1
24.3617044,93.7031143
24.3636391,93.7066297
0.41600642403192
0
Rcc work, wood work, grill

Progress Update : 2017-07-13
On going
1
soccpr1
24.3617044,93.7031143
24.3618018,93.7021912
0.094125147783909
0
Rcc work, wood work, grill

Progress Update : 2017-07-13
On going
1
soccpr1
24.3617044,93.7031143
24.3621018,93.7026165
0.06704334566464
0
Rcc work, wood work, grill

Progress Update : 2017-07-13
On going
1
soccpr1
24.3617044,93.7031143
24.361994,93.7022043
0.097635829478592
0
Rcc work, wood work, grill

Progress Update : 2017-07-13
On going
1
soccpr1
24.3617044,93.7031143
24.3620515,93.7018076
0.13786651780863
0
Rcc work, wood work, grill

Progress Update : 2017-07-13
On going
1
soccpr1
24.3617044,93.7031143
24.3620194,93.7019755
0.12054831064593
0
Rcc work, wood work, grill

Progress Update : 2017-07-13
On going
1
soccpr1
24.3617044,93.7031143
24.3619243,93.7018904
0.12635601184728
0
Rcc work, wood work, grill

Progress Update : 2017-05-17
On going
1
soccpr1
24.3617044,93.7031143
24.3615949,93.703081
0.01263399279245
0
Finishing (Painting) & Electrical Works in progress

Progress Update : 2017-05-17
On going
1
soccpr1
24.3617044,93.7031143
24.3615949,93.703081
0.01263399279245
0
A completed room of a Transit Hostel

Progress Update : 2017-05-17
On going
1
soccpr1
24.3617044,93.7031143
24.3615949,93.703081
0.01263399279245
0
Ongoing Electrical installation works

Progress Update : 2017-05-17
On going
1
soccpr1
24.3617044,93.7031143
24.3638187,93.7064789
0.41401393256269
0
Almost complete Security Barrack

Progress Update : 2017-05-17
On going
1
soccpr1
24.3617044,93.7031143
24.3620392,93.7055474
0.24924214714342
0
Second Security Barrack works in progress

Progress Update : 2017-05-17
On going
1
soccpr1
24.3617044,93.7031143
24.3620417,93.7055491
0.24945404544879
0
Ongoing work of 1(one) of the 4(four) DLO Offices

Progress Update : 2017-05-17
On going
1
soccpr1
24.3617044,93.7031143
24.3629053,93.7059442
0.31621253927782
0
Another DLO Office under construction

Progress Update : 2017-05-17
On going
1
soccpr1
24.3617044,93.7031143
24.3643807,93.7048084
0.34350511374096
0
Almost completed civil work of one of the 4 Nos. of DLO offices

Progress Update : 2017-05-17
On going
1
soccpr1
24.3617044,93.7031143
24.3615949,93.703081
0.01263399279245
0
Transit Hostel Complex

Progress Update : 2017-05-17
On going
1
soccpr1
24.3617044,93.7031143
24.3615949,93.703081
0.01263399279245
0
Multipurpose Hall in progress

Progress Update : 2017-05-17
On going
1
soccpr1
24.3617044,93.7031143
24.3632394,93.7065089
0.38386496627297
0
Almost completed Transit Hostel